Amid global apparel supply‑chain restructuring, Mauritius serves as a key manufacturing hub with favourable EU and US tariff terms. Local garment plants suffer from unreliable scheduling, slow style changeovers, rigid lines, excess WIP and manual handling inefficiencies.

INA completed a challenging delivery for a local customer: 6 smart hanger lines commissioned in only 7 working days (original plan: 10 days), squeezed by a long public holiday. Working three shifts daily, the on‑site team finished installation, testing and acceptance on time. The total solution ran steadily when factory staff returned from leave.

This tailored solution tackles local production pain points on three fronts:

  • Flexible, scalable deployment: Lines can be rolled out gradually starting from one line to match orders and product ranges.
  • Data-connected workflow: Orders, planning and style data integrate with the hanger system for full WIP traceability.
  • Fast mass customisation: Changeover time drops from hours to minutes for parallel small-batch, multi-style production, enabling more proactive order fulfilment.

Drawing on 20+ years of full‑plant smart manufacturing expertise, INA runs a worldwide service network with thousands of completed textile and furniture projects. The Mauritius 7‑day delivery case highlights INA’s reliable execution. We support garment manufacturers globally in digital transformation from OEM to data‑led production, enabled by our deep industry know‑how.